Project Management in Construction M: 7019944355
Need Answer Sheet of this Question paper
Contact us at
M: 7019944355
Project Management in
Construction
Q1. It included Manpower, material and machinery that is
necessary to perform the work:
a. Scope
b. Quality
c. Resources
d. Completion time
Q2. In this analysis a project is formulated and appraised
based on the estimates generated from past data, experience & analysis.
a. Risk analysis
b. Sensitivity analysis
c. Probability analysis
d. Economic analysis
Q3. It is a verbal written or on-line document that shows
the up-to-date performance status of a task that has been entrusted to a
responsibility/accounting centre.
a. Trends Forecasting
b. Reporting Performance
c. Performance Variance Analysis
d. Recording Performance
Q4. In this contract, the architectural and engineering
design and drawings are provided by the
Employer/Client to the contractor at the time of tendering as a part of the
contract documents:
a. Build-only contracts
b. Build-own transfer contracts
c. Engineering Procurement
d. Construction Contract
Q5. These arise where no ground exists either in the
contract or in common law:
a. Contractual claims
b. Extra contractual claims
c. Ex-gratia claims
d. None of the above
Q6. In this case, both the parties willingly discuss the
dispute and arrive at a settlement without the intervention of any third party:
a. Conciliation through negotiations
b. Conciliation through mediation
c. Conciliation by setting up Dispute Review Board (DRB)
d. Conciliation through others
Q7. The claim which is registered by giving a notice is
known as:
a. Registering claims
b. Establishing claims
c. Presentation claims
d. None of the above
Q8. This term covers the entire electronic and electro-mechanical
equipment used in the computerized data processing system:
a. Hardware
b. Software
c. Operators
d. Procedure
Q9. This enables the electronic transfer of a complete file
from one computer to another:
a. Internet
b. Intranets
c. telnet
d. File Transfer Protocol (FTP)
Q10. It is an assurance to the owner that selected the
contractor will actually proceed with the contract at the bid price:
a. performance Bonds
b. Bid Bonds
c. Claim Bonds
d. Contract Bonds
Part Two:
Q1. What are the main causes of a
Project Failure?
Q2. What is Responsibility
assignment Matrix (RAM) chart?
Q3. Define Professional
Construction Management (PCM) approach.
Q4. Differentiate between Project
Management & General Management.
Q5. Should you go with a
department that has been chronically delaying when the contract has a large
incentive/penalty clause for on-time delivery?
Q6. Can you risk sending out a
design to a supplier when the design is to be proved?
Q7. What are the significant
features of HLL’s ad campaign ‘Project Bharat’?
Q8. How has HLL identified itself
with India’s Economic Development?
Q9. Who is a Project Manager?
Describe the Role of a Project Manager.
Q10. What is PMIS Report? Explain
the benefits of establishing PMIS.
Need Answer Sheet of this Question paper
Contact us at
M: 7019944355

Comments
Post a Comment